Fill Dam
How Fill Dam is made
A Dam is a Barrier that is Constructed across a river or stream so the Water can
be held back or impounded to supply Water for Drinking or Irrigation, to control
flooding, and to generate Power. The main kinds of Dams are Earth Fill, Rock Fill,
Concrete gravity, Concrete arch, and arch gravity. The last three types are all
made of Concrete, reinforced Concrete, or masonry. The term masonry can mean
Concrete, bricks, or blocks of excavated Rock.
Dams made of Earth Materials:
All Dams made of Earth materials, Soil, Rock that are compacted together. One type
of Fill Dam called a tailings Dam is Constructed of fine waste that results from
Processing Rock during mining; at mine Sites, this Soil-like waste is compacted
to form an Embankment that holds Water for the mining and milling Processes or
to retain the tailings themselves in Water.
Dams Leakage Control:
Dams that leak have failed to do their job, either because they simply can not
hold Water or because the Water seeping through them eats materials away from
the inside of the Dam causing it to fail structurally.
Fill Embankments are usually Less expensive:
Fill Embankments are usually less expensive to Construct than Concrete Dams. Soil or
Rock are present at the site, and Construction Techniques, though complex, are also
less costly than for Concrete Construction. For these reasons of available materials,
low cost, and stability with mass, Fill Dams are often built across broad Water
courses. They also are more flexible than Concrete structures and can deform without
necessarily failing if foundation materials under the Dam compress with the weight
of the Dam and the Water.
Raw Materials:
The materials used to Construct Fill Dams include Soil and Rock. Soil is classified
by particle size from the smallest, submicroscopic particles called clay; silt,
sand ranging from fine to coarse, where the fine grains are the smallest Soil
particles our eyes can see; and gravel. Coarser Fragments called cobbles and
boulders are also used in Dam Construction but usually as protective outer Layers.
Soil types and size ranges Needed to Construct Dam:
Soil types, size ranges are Needed to Construct the Zones within the Dam, and
explorations of the Dam foundation area, the reservoir where the Water will be
stored, and surrounding areas are performed not only for design of the Dam but
to locate Construction materials. The costs of Fill Construction rise dramatically
with the distance materials are hauled.
Samples of potential Construction:
materials are tested in a Soil laboratory for grain size, Moisture content, dry
Density, plasticity, and Permeability. Clay is not only very fine in size but has
chemical characteristics that cause it to stick together. The combination of fine
size and plastic behavior also causes the clay to be less permeable to Water. If
clay is available near the site, the Dam can be built with an impermeable core or
central Zone that prevents Water from passing through the Dam; the Dam must be
designed so Water can seep slowly and safely through a different combination of
materials in its Zones.
Water Soil also Raw material:
Water is also a raw material. The various Soil types have compaction characteristics
that can be determined in the lab and used during Construction. Soil can be compacted
to its best functional Density by adding Moisture, weight and impact, called compactive
effort. Large vibrating rollers press thin Layers of Soil into place after an optimal
amount of Water has been added. The Water and weight bond the Soil particles together
and force smaller particles into spaces between larger particles so voids are
eliminated or made as small as possible to restrict seepage.
Dams include Geotextiles and Geomembranes:
Dams also include geotextiles and geomembranes. Geotextiles are nonwoven fabrics that
are strong and puncture-resistant. They can be placed between lifts as the Dam is
raised to strength weak materials. They are also used as filter fabrics to wrap
coarser drain Rock and limit the migration of fine Soil into the Drainage material.
Geomembranes are made of high Density polyethylene (HDPE) Plastic and are impermeable.
They can be used to line the upstream face of a Fill Dam or even to
line the entire reservoir.
Feasibility and Preliminary Design:
A specific Need for a Dam, whether it is Water supply, storage of tailings or other
materials, or flood control, stimulates the Process of designing and building a Fill
Dam. The Need and the location are usually closely connected, so several Sites may be
considered. During feasibility studies, engineers identify these Sites, make
preliminary cost comparisons, decide on a probable design, and chose the best site
for exploration. Feasibility certainly refers to the cost of building the Dam,
but it also includes the Technical practicalities of site suitability, design,
Construction, and long term maintenance and safety.
Preliminary Design of the Dam:
After a feasible site is chosen, a preliminary design of the Dam is developed.
The location of the Dam is superimposed on a topographical map, the dimensions
of the top of the Dam relative to the tops of the adjacent hills, the proposed
Water level can be shown as well as the extent of the base of the Dam in the
stream channel. The proposed Water level elevation shows the extent of the
reservoir and determines—along with the shape of the basin—the quantity of Water
that the reservoir will hold.
Quantities of Water and used materials determine the Project cost:
Quantities of Water stored and materials used in Constructing the Dam help determine
the value of the Project and its costs. Sometimes multiple iterations of site
selection, pre-design, and cost estimating are Needed. The foundation area under
the Dam will not require much excavation or grouting to prevent seepage,
and the materials inside the reservoir area can be excavated and used
to build the Dam so that more reservoir storage is gained at the same time
as Soil or Rock are excavated to Construct the Embankment.
Exploration Program is Performed:
When the optimal site is chosen on paper, an exploration Program is developed
and performed. During the exploration, test borings are drilled along the line
of the axis of the Dam across its proposed width, along or near the proposed
upstream and downstream toes of the Dam, at the site of the proposed spillway,
and in the reservoir area.
The Borings are Excavated deep into the foundation:
to evaluate its strength and Permeability properties. As the borings are drilled
through the overlying Soil, it is also sampled and tested in the laboratory so
it can be evaluated as potential Dam Construction material. Field tests of
Permeability are also performed at the site of the Dam and in the reservoir
area. If it is the source for Construction materials, test pits are also dug
in the reservoir area so that the volume of available Soil can be estimated.
Design:
After the laboratory testing are complete, the engineering team begins final design
of the Dam based on the preliminary assumptions, and any changes in design or economics
that are based on field findings. In designing a Fill Dam, engineers look at five
critical considerations: the mass of the Dam that will make it stable; design of a
core and other interior Zones to prevent seepage through the Dam; design of a cutoff
wall or other seepage prevention under the Dam; erosion protection on the upstream
face; and economics.
Fill Dams are typically shaped like triangles:
With the apex or point at the top or crest of the Dam and the broad base on the
floor of the creek channel. The width of the base in cross section provides friction
to prevent sliding, and the total mass of the Dam makes it strong enough to resist
the weight of Water behind it. The foundation area is cleaned of soft, permeable,
and compressible Soil; and a cut-off wall is cut down to Rock or firm Soil.
Fill Dams Consist number of Distinct Layers:
The Zones of a Fill Dam may consist of a number of distinct Layers from the center
of the Dam and moving upstream toward the Water and a different set of Layers from
the center moving downstream. Materials for the Zones are selected for strength
properties and Permeability characteristics, and the placement of one Zone next
to another is carefully governed by sets of calculations based on these properties.
Filter and Drainage Zones are included so that any Water succeeding in reaching
the inside of the Dam is channeled around the core and through Drainage Layers
at the base of the Dam.
Protected with a Concrete Slab:
The upstream face of the Dam is sometimes protected with a Concrete Slab or an
asphalt face. More commonly, cobble and boulder-sized stones are placed on this face
near the Water surface; this facing is called riprap and prevents wave action at
the Water surface from eroding the Dam Construction materials. Other facilities
for controlling the Water level and any Water movement through or over the Dam,
like an emergency spillway, are also designed specifically for the Dams location,
uses, type and materials of Construction, Water inflows into the reservoir.
Construction Materials Available Near the Site:
Construction materials must be available at or near the site. Rock can be placed
at steeper angles than Soil, and it weighs more; so a Dam built mostly of Rock
can be smaller in design section. Excavating and moving Rock can be more expensive
than Soil, so the design engineers must consider cost factors. Other materials
like asphalt, Concrete, steel, and cement for grouting are also expensive.
The proper balance of safety and economy must be determined by the engineers.
Large Earthmoving machines have made Construction of Zoned, Fill Dams more
economical than Construction of Concrete Dams at many Sites.
The Construction Process:
Fill Dams are Constructed in the dry season when Water levels in the river or stream
are lower, rainfall on sources of Fill material is less likely, and conditions are
better for operating large Construction equipment. The site is surveyed to locate
the Dam alignment on the existing ground, the areas that will be excavated, and
the borrow areas or sources for the Soil or Rock used in Construction. Construction
management facilities are set up; usually, the Construction manager will work out
of a trailer on site.
Install Instruments to Monitor the Dam:
Depending on the site, it may be necessary to install Instruments to monitor the
effects of Dam Construction on adjacent hillsides or other features and to measure
groundWater levels throughout Construction in the foundation and surroundings.
Flow of the stream that is being Dammed through the site must be stopped.
This can be done by a variety of methods including diverting the stream, perhaps
to flow through a neighboring channel, or stopping it upstream with a temporary
Dam or cofferDam.
Materials are Compressible and Permeable:
In rare cases, Dams can be Constructed directly on the existing materials in the
channel floor; at most Sites, these materials are compressible and permeable.
The foundation area also includes the abutments, which are the hillsides forming
the two ends of the Dam. Soil and soft or highly fractured Rock are excavated,
sorted by type, and stockpiled for later use in Dam Construction. The surface
of the foundation bedRock is cleaned to a surprising degree; it is broomed and
hosed with Water so that any voids or irregularities are visible
and cleaned of soft Soil.
Foundation is Carefully Inspected:
The foundation is carefully inspected before any Construction work; additional
exploratory drilling may be done if there are any questions about the foundations
condition. If the Rock is fractured or contains voids or holes, these are sealed
with cement Grout that is injected through small diameter Drill Holes
in a Process called Dental work.
Base of the Dam must go Down into the Ground:
The base of the Dam must go down into the ground before it rises above it. A trench
that is the full width of the Dam is cut into firm Rock. The trench is called a keyway
or cutoff wall and may have several benches or notches into Rock. It prevents the
Dam from sliding along a smooth foundation and also creates a longer path for any
seepage to try to flow under the Dam. The impervious clay that will make up the
core of the Dam is placed in the keyway and compacted and raised, Layer by Layer,
until the top of the keyway or base of the majority of the foundation is reached.
Aeriol view of a Planned Fill Dam:
Into the keyway area for the Construction equipment, and then they must be built up
to the working surface of the rising top of the Dam. Roads are cut in from the two
sides of the Dam for the easiest access; eventually, an access road will be built
on the crest of the Dam and extending onto these abutments.
Soil is Spread in Thin Layers:
Large Earthmovers haul the specific type of Soil Needed to raise the Zone of the Dam
they are working on. The Soil is spread in thin Layers, usually 6-8 in (15.2-20.3 cm)
thick, sprayed with Water to the correct Moisture content, and compacted with
sheepsfoot rollers. If gravel is used in Construction, a vibrating roller is used
to vibrate the grains together so their angles intermesh and leave no openings.
Inspectors approve the Soil:
that is hauled on site and hauled to the particular Zone of the Dam. They reject
material that is contaminated with grasses, roots, trash, or other debris; and they
also reject Soil that does not appear to be the proper grain size for that Zone of
the Dam. Samples are collected and tested in the laboratory for a variety of
classification tests. The inspector uses a nuclear Density gauge to test the Soil
for Density and Moisture content when it has been placed and compacted.
The nuclear Density gauge: uses a very tiny
radioactive source to emit radioactive particles into the Soil; the particles
bounce back onto a detector plate and indicate the Moisture and Density of the
Soil in place. The Process is not harmful to the environment or the operator
and provides data without having to excavate and sample. If the compaction
requirements are not met, that Layer of Soil is excavated, placed again,
and recompacted until its Moisture and Density are suitable.
Fill Dam proceeds Layer by Layer:
Construction of the Fill Dam proceeds Layer by Layer and Zone by Zone until the
height of each Zone and, eventually, the crest of the Dam are reached. The Dam is
usually designed in phases or stages. Completing a Construction stage is often a
race against time, the weather, and the Project budget.
Earth Dams have Instruments Installed:
in them at the same time as Fill placement is done, and the Instruments are
Constructed to the surface in Layers and Zones, just like the Fill. The condition
of the Dam is monitored throughout its lifetime, as required by federal, state,
and local laws and by standards of engineering practice.
Types of Instruments:
Vary depending on the location of the Dam; almost all Dams have settlement
monuments that are surveyed to measure any settlement in the surface or Zones of
the Dam, slope indicators to show if the sloping faces inside or on the surface
of the Dam are moving, and Water-level indicators to monitor the Water level
in the Dam's Zones. Dams in seismically active areas may also be equipped
with Instruments to measure ground shaking.
Emergency Spillway is Required:
Fill Dams may have a variety of other facilities, depending on their, size, use,
and location. An emergency spillway is required at all Dams to allow for Flood Waters
to flow over an escape route, rather than over the top of the Dam. Other spillways
for production of Hydroelectric Power may be designed and Constructed, and inlet
and outlet tunnels are Needed to release Water for irrigation and drinking-Water
supplies at Embankments built for those purposes.
Monitored During Reservoir Filling Period:
When the Dam is complete, the Water that was diverted from the stream channel is
allowed to Fill the reservoir. As the Water rises, it is also rising in portions
of the Dam, and Instruments within the Dam are monitored carefully during the
reservoir-Filling period.
Monitoring of the Dam performance: Both by
Instruments and simple observation, is performed routinely; and safety plans are
filed with local emergency services so that sudden changes in instrument readings
or the appearance of the Dam or its reservoir triggers actions to alert and evacuate
persons living in the path of flood Waters downstream. Repairs are also
performed routinely.
Quality Control:
Quality engineering is essential in the Construction of a Fill Dam because the materials
used have lower strength properties than the steel and Concrete required for Concrete
Dams and because placement ultimately determine strength, potential for problems like
seepage and settlement, and finally performance and safety.
The geoTechnical Project: Engineer occupies the key role of making sure the design
and Earth materials match to make a safe product; but many other professionals
including geologists, Construction Technicians, other engineers, and the
representatives of overseeing agencies are fully committed to the same purpose.
Byproducts/Waste:
There are no byproducts in Fill Dam Construction, although Fill is sometimes generated
for building access roads and other support structures. Waste is also minimal to
nonexistent; excavation of excess Soil and especially Rock is very expensive as is
hauling these materials so waste is engineered out of the design.
Wishing you all the best,
http://www.seeyourNeeds.in